Posted - 11/05/2005 : 21:19:33 We will keep this page updated with planned activities on the project.
>> View Pictures of progress here...
Next Sessions -
TBA due to work at home!
- see below for specific tasks
The deck is in and handrail in place some finishing touches required. New gutters, fascias and cladding of the clubhouse have been completed, completion of the access toilet will be the next major push. The key tasks are:
- Inside
- Finish work in lady's changing room
- Box in plumbing
- Work on making new picnic tables
- Outside
- Pipework round rain water collection
- Replace gutter on Drott shed
- Work on outside washup sinks
Please contact me by this link or at premises@greatmoor.org.uk or via the contacts page of this website if you are able to help with the continuing work on the clubhouse. Keep an eye on this listing and we will be pleased to accept your help for any of the tasks listed.
If you can't make the planned sessions we can find a task for you to do at other times!
Order reversed so new items at the top!
TBA 2010 @ 18:30 Connect up weather station Work on new picnic tables Clean up handrail on deck and treat with Teak Oil Improve fittings in cleaners cupboard Work on rainwater collection system Continue boxing pipes in men's Continue boxing pipes in lady's Clean office door
Wednesday April 14th 2010 Pulled through a cable for the weather station Some more work on the new picnic tables
Wednesday April 7th Worked on new picnic tables
Wednesday March 31st Worked on ramp for mirror jetty Worked on new picnic tables
Wednesday March 24th 2010 Worked on new picnic tables
Wednesday March 17th 2010 Fixed frame for storing tables in clubroom cupboard Worked on new picnic tables
Wednesday March 10th 2010 Fixed 3 bird nest boxes to drott shed Re-fix microwave brackets for new microwave Replace seal for door glass on wood stove
Wednesday April 8th 2009 @ 18:30 Move freezers to bar container Install more ventilation ducting above men's changing room Paint weather rail on main door + other
Wednesday April 1st Rub down and oil new doors in clubroom Routed new cable into Drott shed Measured up some items for futere tasks Changed PIR on lighting in men's changing room
Wednesday March 25th Connected power to Bar container ready for freezers to move back Connected extractor fan in Men's Fitted 4th loud speaker on wall in clubroom
Sunday March 22nd Connected cable to bar container Filled round weather strip on main clubhouse door
Friday March 20th Fitted new threshold strip on main door to clubhouse Modified base of main door to clubhouse
Wednesday March 18th Filled some holes and in plasterwork Filling round ducts in men's changing room wall Painted part of wall in men's changing room Connected cable to fan in men's
Tuesday March 17th Tidy up round lower steps to lowest trott
Friday March 13th Helped load some surplus items sold on e-bay Isolated problem with phone wiring Printed missing renewal invitations
Friday March 6th Finished gutter at rear of bar Finished work on stove Loaded more scrap metal in the skip
Wednesday March 4th Printed membership renewal invitation letters
Wednesday February 25th @ 18:30 Continued assembly of ramp for main jetty Measured up and other prep. for work day materials
Wednesday February 18th Constructed a stand for new folding tables Started assembly of ramp for main jetty Some measuring up
Wednesday February 4th Some work on electrics Started testing Electrical Installation
Wednesday January 21st Some work on electrics
Wednesday January 7th Did some small maintenance tasks Unloaded pontoon ramp from Dave's van
Saturday December 13th Windowsill installed in Lady's More boxing round plumbing and ducting in Lady's Ventilation duct started in Men's #5 buoy replaced Tarpaulin cover on portacabin fitted
Friday December 12th Work on tiling in lady's
Wednesday December 10th Continued work on woodstore
Friday November 28th Cladding of back wall and Southern end of clubhouse completed Fascia at back of clubbhouse in place Fixed key box to wall
Wednesday November 26th Continued cladding Continued work on new wood store
Sunday November 23rd Completed woodstore roof
Friday November 21st Constructed woodstore roof and partly covered
Wednesday November 19th Continued cladding
Monday November 17th The contractors installed the gas heater in the lady's changing room Did some work on new wood store
Saturday 1st November Workday Prepared and ate lunch Clear area by small wood store ready for gas heater install in lady's Moved bar container to new location Fitted gutter to front of Clubhouse Improved hand rail at top of steps More cladding on north end of clubhouse Completed concrete work around new pontoon ramp Cleaned out freezer, fridge and cupboards in galley Fitted new terminal guards on heater ports Formed bases for new wood store and cemented in place Cleared up where bar store has moved from Replaced #3 buoy Replaced faulty emergency light in men's changing room Put pea shingle round new concrete
Friday October 31st @ 10:30 Continued installing ventilation ducting in lady's Continued install of cladding Installed new fascia on front of Clubhouse Installed external sockets on clubhouse front wall Modified internal wiring on bar container
Thursday 28th day Assist Pioneers Continue cladding
Wednesday October 29th Measured up and prep for workday 1st Nov
Wednesday 28th day Assist Pioneers Continue cladding
Tuesday 27th day Assist Pioneers Start cladding
Friday October 24th Some preparation for cladding Assist pioneers with concreting Construct shuttering for new pontoon mooring Unload featherboard for cladding
Wednesday October 22nd Continued installing ventilation ducting in lady's
Wednesday October 15th @ 18:30 Continued installing ventilation ducting in lady's Measured up for detail of cladding Continued battening outside walls for cladding Did some planning for Pioneer work 20th onwards
Saturday October 11th Grass cut around entrance Some berths tidied up Temporary pergola taken down New gutter fixed to front of clubhouse 10t shingle spread in car park Last of the spindles fixed round the deck Extractor fan installed in lady's (hole through wall and temporary wired to lights) Cabling run for external sockets and lighting on front of clubhouse Base of flagpole repaired Deck boards of phase 2 trimmed to length and ends treated Base of water tanks treated 3 kestrels upgraded Lunch eaten (thanks Sandy) Some more battens fixed to front of clubhouse Willow rings moved Hawthorn tree next to steps pruned Race board stand repaired Removed old gutter around men's changing room Investigated fascia above office door  and ....
Friday October 10th Last of spindles for deck finished
Wednesday October 8th Installed wall plate for projector connection and tested Checked faulty emergency light - its faulty Found clamps for fencing Planned some materials for Saturday
Friday pm October 3rd Fixed last two sections of bottom rail of decking edge Finished some more bars for deck rail and installed 36 more (that's about 130 so far)! Removed last of Harris fence panels from edge of decking
Wednesday Evening October 1st Base for heater in lady's in place and coat of primer Duct for ventilation fitted in lady's Some of the plumbing coverd in the men's Remaining bars for deck railings rut to size Kestrel turned over in Drott shed
Wednesday Evening September 24th Finished and fixed some more bars on the decking handrail
Friday Evening September 19th Completed fitting decking handrail along remaining of deck front First section of bars under deck rail inserted
Wednesday Evening September 17th Some wood cut for decking handrail
Saturday 13th September The rest of the deck structure in and boards in place - a long day - but its in! Top of handrail fitted
Friday 12th September 15:00 The next beam was fixed in place with some joists and hangers in place
Saturday 6th September (workday) Dug trench for cable to new bar container location Car park leveled Drainage channel dug Cable duct put in place Another 2.4m of deck built Some work on new wood store
Friday 5th September Started structure for phase 2 decking Started constructing base for heater in lady's
Tuesday 2nd September Dug drainage channels in area of phase 2 decking and filled with pea shingle Dodged the showers
Monday 1st September Malcolm built new casing for manhole cover to drains
Tuesday 26th August Did some clearing up of demolished portacabins
Sunday 24th August Located IBCs on newly constructed pad
Tuesday 19th August Put up the second section of shelf in the lady's
Wednesday 9th August Started on the urinal flush control Raining so no outdoor tasks done
Tuesday 1st July Fitted handrails and did some other finishing work on and around decking Painted timber work around urinals in men's Finished installation of Urinal plumbing
Work session @ Junior Sailing Saturday 28th June 10 o'clock (10:00) Unloaded decking timber from lorry Finish decking structural timber work for phase 1 Fitted deck timbers to phase 1 Fitted some handrail to decking Removed old gutter and fascia from part of clubhouse front, fitted new fascia backing Moved 'spare' timber and other materials from men's changing room Grass cutting Another coat of paint on timber work around urinals in men's Removed some old cement then turf old steps area for portacabin Weld up security grill Made some 'polite' signs for changing rooms Moved another load of soil and hardcore to DBP
Friday 27th June Put the rest of handrail posts round phase 1 decking area Dug/concrete last foundation pad for phase 1 decking
Tuesday 24th June Continued construction of decking - - Added front rails and an intermediate post for handrails, - Add noggins on most of the joists - Filled woodwork on panel for urinals - Started the plumbing for urinals
Sunday 22nd June Continued constructing decking beams and joists for first phase of decking - all beams in place, most joists in place, some handrail posts fitted
Work session Saturday 21st Good progress after a few initial hitches, 3 of the four planned bays of joists in place - you can just see them on lakecam (2) (pictures to follow) Drainage vent stack replaced to allow cladding and be ready for installation of urinals Undercoat applied to new area for urinals
Tuesday 17th June Started on lady's shelves Finished woodwork around men's urinals - now ready for painting
Work session at Junior Sailing Saturday 14th Finished painting the race hut Finished painting the security grills Fixed wall plates for first stage of decking Did some battening outside walls for cladding Tidied up round moved portacabin lots of grass cutting and .........
Work session at Junior Sailing Saturday 7th June Made pads for decking on Patio area (Cut hole, dig down, fill concrete *10) Cut some grass Cleaned the Race Hut (outside) and started painting it Painted one of the security grills Trimmed some trees
Tuesday 3rd June Did some more work for the urinals
Workday Saturday 31st May thanks to all that attended Spread new shingle (20t) in car park Disconnect portacabin door links ready for large cabin to be moved Sealed up link doorways on portacabins Moved 3 boats to allow repositioning of large portacabin Cleared out below large portacabin Made pads for new position of large portacabin Made shutter boxes for concrete pads Made pads for decking (drilled holes with post hole borer , fill with concrete and rebar) Battened the back wall of men's changing room ready for cladding Trimd small trees in front of race hut (see results on lakecam I) Cut grass around clubhouse etc. Varnished shelves for lady's changing room Rodded the drains! Filled along back edge of mantle shelf Changed screws in lady's shower pole base to stainless Painted back door of men's changing room Put plastic buttons on cubicle fixings Tidied up patio area
Thursday 29th May Bob tiled the piller in the men's changing room
Tuesday 27th May Did some planning for Saturday Asked intruders to leave site
Tuesday 20th May Started work on Urinals Hung shower curtain in Lady's Fitted button for Projector screen
Wednesday 14th May tidied up for Junior sailing on 17th! Started plumbing in lady's showers Started installation of mantle shelf in clubroom Rubbed down and oiled new bar door
Tuesday 6th May Preparatory work for installation of lady's showers Measured up for some plumbing and ventilation materials
Friday 2nd May Gloss paint on lady's change door and frame More work on toilet cubicles (all doors on) Painted round tiled panel in lady's
Wednesday 30rd April More work on nstalling the toilet cubicles Continued cleaning up and filling door frame on lady's changing room door Undercoat on partition of men's toilets
Wednesday 23rd April A little work on the toilet cubicles More tiling in lady's shower (now grouted) Some cleaning up and filling door frame on lady's changing room door Undercoat on toilet divider in men's Some filling done round tiled panel in lady's
Sunday 20th April Connected hand dryer in lady's cable trunking for thermostat in men's wiring tidied up on bar door Toilet roll holder fixed in mens cubicle
Friday 18th April Continue install of toilet cubicles access control completed on replacement Bar door
Wednesday 16th April Started install of toilet cubicles More tiling in lady's shower
Some filling and priming around ladies shower area
Wednesday 9nd April Painted on architrave on disabled toilet door More tiling in lady's shower Installed and checked Emergency light in Lady's Shelves for lady's assembled Modesty panel for lady's shower area readied for tiling edges fitted and profiled, primed all bare wood Some painting in Men's changing room
Friday 4th April Bob in the afternoon then Malcolm, Tony Some more work on boxing in pipes in lady's Tiled the back wall of lady's shower area more work on bag shelf for lady's changing room Fix brackets for mantle shelf Modesty panel in men's painted Door to men's changing room given a coat of gloss Coat of pva on panel in lady's ready for tiling
Wednesday 2nd April Malcolm, Tim, Tony More painting done Started work bag shelf for lady's changing room Some work on lady's shower area Started to box in some of the pipework on lady's
Thursday 27th / Fri 28th March Hooks fitted to new benches in lady's Undercoated architrave on disabled toilet door Another coat of terracotta on mantle shelf Some more work done on modesty panel in lady's Cubicle partition in men's primed Rubbed down and painted back door to men's changing room Another coat of undercoat ends of modesty panels in mens Decided how to fit Emergency light in Lady's Emergency lighting in Men's connected up and working
Wed 26th March Two coats of varnish on new benches in lady's Undercoated architrave on disabled toilet door Another coat of terracotta on mantle shelf Some more work done on modesty panel in lady's Fitted PIR sensors in men's Rubbed down and apply another coat of gloss new door on disabled toilet Another coat of undercoat door on lady's changing room Rub down and paint back door to men's changing room Cleaned up and did more filling on door frame on lady's changing room door Undercoated and filled ends of modesty panels in mens Emergency lights fitted in mens
Wed 19th March Rubbed down and varnished (first coat) new benches in lady's Cut and fitted architrave on disabled toilet door First coat of top coat on mantle shelf in terracotta fitted end covers on panels in men's Gloss new door on disabled toilet Undercoat door on lady's changing room Re-fixed base of RH heater in men's
Friday 14th March Malcolm, Tony Last tiles ni men's shower grouted Men's shower silicon sealant run at ceiling First bench in lady's completed (well nearly) Second bench in lady's to same state ....- just needs hook rail to be ready for rub down and varnish Modesty panel in lady's -frame fixed in place - now needs bracing and cladding
Cleaned up, filled and primed door frame on men's changing room door
Wed 12th March Bob, Cliff, Stuart, David, Tim, Malcolm, Roger, Sue, Tony Pulled through cable for thermostat in men's changing room First gloss on new door on disabled toilet Primed door on lady's changing room More undercoat on modesty panel in men's Fitted rest of light fittings in lady's Started making new benches for lady's changing room Insulated pipes above mens toilet cubicles Closed some ducting in lady's Labeled mail shot More Tiling in men's showers
Friday 7th March Malcolm and Cliff assisted and: Grouted tiles in men's shower Put closer and handle on door to lady's Did some cleaning up and put remains of old flooring into bin Did some more work on end partition of mens Cubicles
Thursday 6th March Bob spent some time at the club and: Put undercoat on new door on disabled toilet Rubbed down and varnishing last new bench in men's changing room Painted ceiling in men's shower area Put second coat of emulsion on end wall of men's
Wed 5th March Stuart, Colin, Malcolm, Ian, David, David, David, Tim, Tony, Tony, Cliff, Roger and Sue Finished install of toilets, plumbing in and test More work done on partition for end of men's cubicles Fitted new door on lady's changing room Done more work on modesty panel in men's
Modified and fitted last door on kitchen units First new light fitting installed in lady's Tiled extended area of men's Temporary 'screens' erected around toilets Fitted additional shelf in cupboard under urn
Sat 1st March Roger, Stuart, Colin, Wally, Andrew, Adam, David, David, Paul and Tony The floor laying was completed by John the floor layer Put a coat of paint on the walls in the cleaners cupboard and clubroom cupboard Painted the ceiling in the men's shower Stuffed the renewal letters into envelopes Painted the end wall in the men's changing room Cleaned and replace cooker in Galley Put dishwasher and fridge back in galley Moved some tables and chairs back into clubroom Ran pipework for new cisterns in mens Ran pipework for new cisterns in lady's Started installing toilets, found problem with fill rate Put up first part of partition for end of men's cubicles Put back doors in men's and old lobby Put benches back in place in men's Re-assembled central benches in men's Put Legs on L partition in men's Put up modesty panel in men's still needs completion (pull through cable for thermostat and fit box) Rubbed down and varnished last new benches in men's changing room (still needs last coat) Completed fitting new door on disabled toilet Some work on getting power boats back on the water and ate a very good lunch cooked by Wally
Sun 24th February Clubhouse was cleared ready for the new flooring to be laid Moved fridge into Bar Stacked short benches in shower area Moved cooker and dishwasher int old entrance loby Old floor taken up in clubroom Finished painting wall and partition at far end of men's changing room Painted new plasterwork in lady's Painted ceiling and new cubicle walls in men's Started construction of frame for end of cubicles in men's Undercoated mantle shelf Started battening outside walls for cladding
Sat 23rd Feb Access control for Bar installed More prep for floor laying done
Fri 22nd Feb Radio aerial installed More network cabling finished Cable run for Bar access control Some changes made to plumbing for new toilet arrangements
Wed 20th February 6pm onwards Fixed new light fittings in men's Painted first coat on new plasterwork in lady's Painted ceiling and new cubicle walls in men's
Tuesday 19th February Additional coat of paint on men's ceiling and walls
Sun 17th February Skimmed new plasterboard in lady's Started constructing modesty panel for mens Completed base timberwork for new benches in lady's First coat of paint on ceiling in men's Repaired insulation in roof from breakin Fitted Cabin Hook on fire exit door Mounted new shower heads in men's showers Fitted trim strip to remaining joint in galley wall lining Investigated external vent pipe adjacent men's change decide modifications to enable cladding Undercoated mantle shelf Did some tidying/clearing up Squared of ends of central bench in men's Ran cables for new light fittings in men's Repaired loose patch of floor screed in men's Fixed battening on wall in lady's shower, insulate, fixed Aquapanel Removed door of lady's changing room Lots of tidying up of cable runs
Fri / Sat 15th 16th Feb Chased out for wiring in lady's changingroom Battened and lined wall in lady's Plasterboarded new partition in Lady's Extended step in entrance to men's changingroom Fitted new light switch in lady's
Wed 13th February Skimmed plasterboard behind men's toilets PVA applied to ceiling in men's Fitted new drain in lady's shower area Completed wiring for network link to Drott Shed Mounted access control unit for Bar Fitted soft close stops on galley cupboards Primed mantle shelf Constructed stud work for edge of lady's shower area Taken up remaining floor covering in lady's Set floor gulleys in men's Started running cables for new light fittings in Men's Tidied up wiring above fuse cupboard
Sun 10th Feb Dry lined wall in Mens next to toilets Removed vinyl floor cover in in men's and most of lady's Removed hand dryer and electric heating from lady's Completed surround for new lady's shower area Made good wall outside lady's Removed some old tiles from men's shower area
Sat 9th February Modified pipework above toilet area in men's Built stud work behind toilets in men's - and fixed plasterboard Plasterboarded stud work in lady's Removed basins in Ladies to allow work Cut back concrete ready to fit new drain in lady's shower area Dug out old floor drains in men's Set up Temporary toilet facilities Removed collars from soil pipes in mens change Removed vent pipe in lady's and modify pipework - made good wall inside
Wed 6th February afternoon/evening Finished wiring for trace heating on water heater Removed lights in men's changing room Fitted some stud work in lady's changing room Leveled floor in mens change ready for floor laying Primed disabled toilet door Primed some timber work in clubroom Added more timber to cupboard area in clubroom Sorted materials order list for weekend work Fitted remaining trays in cup cupboard
Sun 3rd February Fitted hooks on finished new benches in men's Removed benches from lady's Started to set up Temporary toilet facilities Removed toilets from lady's Fitted weather rail on lakeside doors Completed install of last bench in mens changing room Started to fit new door on disabled toilet
Thur 31st January More paint put on wall of men's Outside tap remounted
Wed 30th January (evening) Sorted out the dishwasher! Some planning for the workdays. Removed toilet cubicles from men's changing room Completed temporary light in old entrance lobby
Tue 29th January Continued rubbing down and varnishing new benches in men's changing room Continued painting new plaster in men's changing room
Wed 16th January First coat of emulsion on new plasterwork in men's Rubbed down last benches Chopped in cable runs and backing box for some electrics in men's Planning for new cupboards in clubroom
Tuesday 15th January Malcolm cut back shower area in men's changing room
Wed 9th January Finished wiring for trace heating on water pipes in roof over men's changing room Continued with installation of new benches in mens changing room Removed a section of wall adjacent to showers in men's Caught and ejected a mouse Tidied up the inside of the cupboard in the clubroom
Tues 8th January Bob put a first coat of varnish on the last benches in the men's
Thursday 3rd January Paul and Malcolm dry lined and skimmed the rebuilt partition and the wall adjacent to the office in the men's changing room
Wed 2nd January Made temporary repair to race hut window Rebuilt partition by fire exit in men's changing room
Wed 12th December Removed the last of the old benches from the men's changing room Made the last two sections of benches for men's changing room
Wed 5th December Tasks available: Started wiring for trace heating Removed some more of the old benches in Men's changing room Built another section of new bench in men's changing room Rubbed down and start varnishing another of the new benches in men's changing room More filling and finishing of the door frame of mens changing room door
Wed 28th November Built another section of bench in men's changing room Modified central bench in men's to allow floor to be fitted More filling around new door to Men's changin room
Wed 21st November (evening) Rubbed down and start varnishing new benches in men's changing room Continued painting door to men's changing room Made bracket for projector screen Bob finished the benches on Thursday and Friday
Wed 14th November (evening) Finish insulated more water pipes Fitted Cabin Hook on mens change door Continue building more sections of benches in men's changing room Made good wall in men's changing room Malcolm has filled in some of the holes in the floor Bob did some more work on the Store cupboard in lady's changing room during the week
Wed 7th November (evening) Fitted out modified Cupboard in Galley Started work on next benches in Men's Some of the holes filled in the men's changing room floor
Tues 6th November Bob spent a few hours in the afternoon and Primed the new door to Mens changing room Cleaned up, filled and primed the door frame of Men's changing room door.
Wed 31st October (evening) Wired up temporary external light by lakeside door Fixed hooks to new bench in Men's changing room More work carried out on electrics Added shelf in main cupboard in Clubroom
Wed 24th October (evening) Fixed bases for new benches in men's (cut timber, fix to wall) Cleaned tiles in Men's shower - decision keep and re-grout Fixed some wiring in ceiling of main room in preparation for link to Drott shed Discussed detail of cladding and did some planning of cupboards in main room Bob has been varnishing the new benches
Wed 17th October (evening) Extended hearth (completed Friday) Fill bottom of walls in clubroom Started wiring up external lighting control Removed ceiling in old entrance lobby Replace broken up-lighter
Wed 30th May (Evening) Completed installation of access control for clubhouse Mounted fire blanket in Galley Insulated new plumbing in men's Finished off around wash basins in men's
Wed 24th May (Evening) Worktop for wash hand basins replaced in ladies, External reader mounted, wired up and tested for club house access control Tiled round mens wash basins
Saturday 19th May - Junior Sailing Men's toilets cleaned up and a coat of emulsion Pipes lagged in men's. Wood store tidied and extension built Internal reader for access control to clubhouse connected and tested
Work session Wed 17th May (Evening) Another coat of emulsion on the walls in the men's Tile round new wash basins in men's Access control unit mounted and power supply connected Door release mechanism connected and tested
Sat 12th May Installed wash hand basins in men's changing room (cut through walls for pipe runs etc) Fitted a urinal temporarily in men's Removed both of the old wash hand basins in the men's fitted new escutcheons on lakeside door lock
Wed 9th May Started work on new wash hand basins in men's changing room Shutter now working on Patio door More painting done including first coat on new plaster work in men's Cleaned up and primed cover over beam cross galley
Sat 5th May Plastered remaining areas of dry lining in men's changing room Ran electrical supply for access control/alarm Mounted access control unit for lakeside door Connected up flood light on car park side of clubhouse
Note - no session Friday 4th May due to training course
Wed 2nd May First thinned coats of emulsion on plastered wall in men's changing room Finished lining walls in galley Fit Latch in cupboard door in lady's changing room Primed outside of door in lady's changing room. Pulled through cables for egress lights (men's change back door and office door) Made and mount backing board for new notice board by phone (one of the old notice boards fixed in place).
Saturday 28th April Installed down lighters over phone/noticeboard Finished battening and lining men's changing room Fixed vents/flaps on outside for Lady's extractor Plastered area in Men's where new wash hand basins will go
Friday 27th April (Evening)
Wednesday 25th April (Evening) started install down lighters over phone/noticeboard Finished fixing the third extractor in the galley Cut in backing box for fridge supply Continued battening and lining men's changing room Did some more painting round the clubroom Fixed vents/flaps on outside of galley extractors
Friday 20th April (evening) Clubhouse is readied for topper open Installed 3rd extractor hood in galley
Thursday 19th April More painting
Wed 18th April (Evening) Painted undercoat on beam between bar area and main area Descaled shower heads men's change Painted wall adjacent to bar Fixed plinth for heater in main room and move heater from Drott shed Cut in electrical boxes for up lights, Fixed uplights Continued battening and lining men's changing room
Sat 14th April More battening in men's
Fri 13th April (Evening) Made sure the club is fit to welcome visitors for the Champion Club event on Sat 14th Lakeside door lock sorted (mostly) Key box fixed to wall First aid box fixed to wall Fixed door closer on lady's change door Fixed door closer on Lakeside door Main light switch panel wired up Tideied wood store
Wed 11th April (Evening) Cooker installed Commission galley extractor hoods Fitted door furniture on new fire exit door Did more electrical installation Continue battening and lining men's changing room
Friday 6th April More painting done to walls in clubroom More painting done on outside doors Installed Dish Washer Started install of third camera Completed installation of extractor fan in lady's changing room Moved phone Routed cables for access control Connected door release for lakeside door Did some clearing up Commissioned new urn
Wed 4th April (Evening) Continued battening men�s changing room Did more Painting walls in clubroom Did more paint on outside doors Did more electrical installation Did more work on the Galley Mounted microwave on wall in galley Tested new urn (found that the filer hose leaked) Met with MD of Gas Installation Company to discuss work Fettled fit of lakeside door
Sat 31st Plastered around phone position, and alongside bar and anything left from the list below Continued battening men�s changing room and put up some plasterboard More Painting walls in clubroom More paint on outside doors Conmpleted new doorway and stud wall for disabled toilet (woodwork) Wiring for speakers and network connections carried out More work in the galley completed
Wed 28th March (Evening) Insulated remaining pipes in lady's changing room Continued battening men�s changing room Painted walls in clubroom Did more electrical installation
Fri 23rd(eve) Sat 22nd March Rubbed down and paint doors (next coat) Wall either side of Chimney breast painted Made good threshold on new fire doorway Made good walls in men's changing room ready for battening Continued work in Galley Started new doorway and stud wall for disabled toilet Completed plasterboard on wall by phone
Wednesday(Eve) 21st Rubbed down and painted doors Made good thresholds of lakeside door Started battening men�s changing room Continued work in Galley Hand dryer in Lady's changing room connected up Box mounted for thermostat in Lady's changingroom Started new door frame for new doorway for disabled toilet Put undercoat on L wall in men's changing room Grouted tiles in bar
Friday 16th (Afternoon/Evening) Saturday 17th Rubbed down and painted doors Insulated some pipes in lady's changing room Fixed remaining lights to ceiling Tiled lady�s splashback and bar splashback Moved sockets in bar Made improvements to HW plumbing Plumbed in waste for new urn Fitted cupboard shelves under three sinks Battened area near phone and cleaned up and moved phone Continued work in Galley
Thursday 15th Malcolm has done a posh job on the Chimney breast Rendered some of the old window areas in the men's
Wednesday 14th (Evening) Cut in many of the electrical boxes to walls Started wiring sockets etc in clubroom Paint L shapped divider in Men's changing room Added plumbing for dish washer Wired in outlets for heaters and hand dryer in Men's Fixed outlets for heater and hand dryer in Lady's Planned tea/coffee making area
Sat 10th March Refixed frame of Lady's changing room door Remaining plasterboard fixed Walls Plastered Small central wall in men's changing room cut back Latch for lakeside door fitted New heater fixed to wall in lady�s changing room Primed inner face of L shapped divider in Men's changing room
Fri 9th March (evening) More electrical work done including power to the boiler Sinks fitted in the galley Preparation for plastering Started fitting lock / latch to main door The gas is on and we have heating in the gents and instant hot water throughout Sinks in galley plumbed in Another Screwfix order is being put together...
Wed 7th March (evening) New extractor fan in lady's changing room partly installed. More electrical installation completed Anti-scale device fitted to mains water Boxing to plumbing modified and refitted in office Network cables tidied up in office Pulled cable through to form new lighting feed to men�s changing room More of the plasterboard fixed including the pads for fire extinguishers Hand dryer fixed to wall in Lady's changing room Lady's changing room tidied up
Sat 3rd Mar The ceiling was plastered and lights fitted Wall each side of fireplace plastered Staging removed New wash basins in Lady's changing room fitted Tank connected for feed to cisterns Kitchen fitting progressing well Tidied up for Sunday - inside and out Trace heating wire pulled through Temporary enclosure round electrics
2nd March Kitchen install started
1st/2nd March Gas heater installation started - slow progress
28th Feb (evening) More of the plasterboard fitted Lakeside door hung More electrical installation completed More battening fitted in the kitchen Plumbing ready for gas install and commisioning
Wed 28th New windows fitted to men's changing room
Sun 26th General workday Lakeside door cut to size and edged, painted on one side Fire door fitted, hung and first coat of paint applied Some of the last bits of dry lining installed. More electrical cabling installed including run for trace heating Temporary steps installed for patio door and lakeside door More battening in place around fire door and some in galley Much of the old benches removed from men's changing room Some old timber cut up for firewood Rubbish put in skip Building blocks moved
Sat 25th Feb Main room dry lining nearly completed plastering next Saturday Complete construction of platform for CW tank (timber work) Water heater mounted and much of the plumbing for it in place
Thursday 22nd/ Friday 23rd Holes cut for new fire exit door and new windows in men's changing room.
Wed 21st Feb (evening) Batten East wall for plasterboard (drill plug wall screw batten to wall). Continued the installation of cable runs in main room area Marked positions of new windows on wall of men's changing room. Install new extractor in lady�s changing room Battened north wall to left of fireplace ready for plasterboard
Monday 19th The patio door and window were fitted
Sunday 18th Feb Holes for sink wastes in Lady's changing room cut. Old extractor hole fully closed and a number of other old holes made good. More of the joist in the roof in place (nearly all done now). More of the cabling in place. Tank support structure in place, just needs a 'floor'. Cable ducting for distribution panel in place. Cut hole in wall for tank overflow.
Thanks to Alison, Brian, Robin, Tim, Tony, and Tony. David was working on the committee boat, we saw him when the soup was served!
17th Feb First day of work after the new holes cut in the wall! a bit cool. lots of dust from the disk cutter we will have to do some serious cleaning up soon. Good progress today: Holes cut in wall for extractors and waste pipes in galley New main door frame fitted Insulation in roof now completed Roof joists fitted to lakeside, only galley side to do Support for new water tank started Lots more of the plumbing in place Frame to support cooker hood started. Cavity closers fitted to new openings. Base of opening for patio door cleaned up. More of the old wood cut up for the fire.
Thanks to those who helped today (Dan, Cliff, Colin, James, Malcolm, Mike, Paul, Ron, Simon, Stephen and Stuart)
16th Feb Day 2 of the building work Eddie cut hole for new window and modified the lakeside door opening for new door. Had a 07:45 meeting with heating engineers about installation of gas space and water heaters. David W making and fixing plates to mount main lights on. Cliff did more plumbing.
15th Feb Builder (Eddie) started work on modifications to lakeside wall for new windows and doors. Cliff worked on plumbing and David W ran some cabling.
14th Feb Lower insulation installed on east side, holes drilled for some of the pipe runs. Window positions marked and mixer found and started.
10th/11th Feb The final roof tie is in place and wall plates on north wall to support ceiling joists. Small holes in roof sealed. Centre ceiling joists in place and centre runs of roof insulation fitted. Ventilation holes for roof space have been cut. Airbrick in fireplace finished. Fix wall plate for cold-water tank support. Old extractor fan hole on wall bricked up. 7th February All but one of the roof ties are now in place. Extractor removed from galley, tiles removed from lady's changing room. More of the re-cabling completed. Floor in old cleaners cupboard filled.
4th February First planned Refurbishment work session. Following the success of the workday on the 3rd the remains of the clubroom and galley have been stripped out and the first two of the new ties have been put in place in the roof. Much of the old timber that was taken out has been cut up and put in the wood store for burning on the wood burner. More work on the construction of new steps to the portacabin was completed.
3rd February Good progress made at the workday, clubroom cleared, low ceiling, tanks and wall removed. Part of main ceiling cladding also removed.
28th January New windows ordered.
17th January Building control approval received!!!! Strip out of galley and tanks etc planned for 4th Feb
See http://forum.greatmoor.org.uk/topic.asp?TOPIC_ID=522 for earlier activities...
|
|
|
|